By Daniel G. Teleoaca — Chief Engineer Unlimited

There’s a moment every Chief Engineer knows, but you’ll never find it in a training manual: the actual handoff.

Not the classroom handoff. Not the “everything is fine” checklist handoff. I’m talking about the real moment you walk into an engine room that should be running perfectly, but within five minutes, you smell something that screams “not fine.”

We’ve all taken over ships after long vacations, after chaotic crew changes, and after shore-based “efficiency initiatives” had stripped the soul out of the engine room. We’ve stepped onto vessels that looked immaculate on paper and others where the bilges would embarrass an abandoned drydock. In every single case, how we handled that transition defined our first 72 hours—and our reputation for the rest of the contract.

Here’s the battle-tested approach I use to take command of a ship the right way—without losing my sleep or my authority.


Ask the Questions the Manual Doesn’t

Standard practice relies on checklists: bell to bell, alarm tests, PMS status, spare parts inventory. But checklists only repeat what the crew thinks you want to hear. Questions reveal what they actually do.

When I walk the plates with the outgoing Chief or the 1st Engineer, I skip the “is it working?” fluff. I ask:

  • “What do you think is going to fail the moment I’m asleep?”
  • “Where are the chronic alarms you’ve started to ignore?”
  • “Which specific machine makes you nervous when we’re at 85% MCR?”

Those questions bypass the “Standard Operating Procedure” and expose the engine room’s true blind spots. People rarely lie about what keeps them up at night.


Start with the Bilges (The Forensic Audit)

You think bilges are just about housekeeping? Think again. To an experienced Chief, the bilges are a forensic record of the last six months.

The bilges tell me:

  • How disciplined the crew is.
  • How many “temporary” leaks have become permanent fixtures.
  • Whether the PMS is actually being executed or just “clicked” away on a computer.
  • The reality of the steam, water, and oil interfaces that everyone else is ignoring.

If I walk in and the bilge is sitting at 30–40 mm anywhere other than the sump, I don’t see a mess; I see a failure in root-cause culture. Fixing the symptom (pumping it out) does nothing. You have to kill the source. My first shift usually involves a “Bilge Improvement Stand-Up.” It sets the tone immediately: We don’t live with leaks.


The “10-24 Rule” of Leadership

Every ship has a mechanic who knows every pump, valve, and breaker better than the drawings. Your job isn’t to out-mechanic them—it’s to focus their wisdom.

REMEMBER: Authority is a rank, while Leadership is a rhythm.

I follow a strict “10-24 Rule” for every takeover:

  • The First 10 Hours: Shut up and listen. Don’t change a single major setting. Watch how the crew moves. Observe the “unwritten” rules of the engine room.
  • The First 24 Hours: Fix the obvious “Reliability Killers.” Clear the bilge drains, address the overdue critical PMS, replace the worn-out tools, and fix the missing tags.

Once the crew sees you fixing the things that actually make their lives easier, they’ll follow you into the difficult jobs.


PMS is a Tool, Not the Destination

Planned Maintenance Systems (PMS) are a guide, not a God. I’ve seen too many Chiefs mistake a “100% Green” logbook for a healthy engine room.

The real metric isn’t your compliance percentage; it’s Failure Avoidance.

✅ No unexpected stops.

✅ No “workarounds” that have lasted more than a week.

✅ No “noise” in the system.

If your PMS is screaming alerts for items that never fail, it’s just noise—clean the database. If a component fails twice a month despite being “in the green,” it’s not a maintenance issue; it’s an operational or design flaw. Real success is going six weeks without a single “surprise” alarm.


Culture Over Compliance

I once took over a vessel with 98% PMS compliance, yet an auxiliary engine stopped twice in my first five days. When I asked the engineers, they pointed to the screen and said, “But the system says it’s okay.”

That’s a culture problem, not a technical one. You build a reliability culture by:

  • Rewarding Proactive Fixes: When a 4th Engineer tells me he rerouted a cable because it was vibrating against a pipe—that man gets my full support.
  • Sharing the Truth: Discuss the data weekly, not just when the office asks for a report.
  • Acknowledging the Grit: Realize that a clean engine room is the result of people who care, not just people who follow orders.

The Bottom Line: Command is Earned, Not Issued

A Chief’s first watch isn’t about checking the equipment; it’s about earning trust. Trust from the crew that you know your stuff, and trust from the company that you’ll keep their ships moving.

You don’t earn that trust by ticking boxes on a tablet. You earn it by showing that you can diagnose reality, lead a team through the grit, and fix what’s actually broken.

Because at the end of the day, the ship doesn’t care about your rank. It only cares about the man who knows why the pressure is dropping.

If you want a companion workflow to systematically audit your engine room on the first day, subscribe and reply to this article. I will send you the Chief Engineer Handoff Audit Checklist.

Similar Posts

2 Comments

  1. Good Article Sir. I want to ask an opinion from you. I am a Second Engineer. Recently, there was a job in PMS to overhaul Emergency Fire Pump Motor. But please note this pump rarely runs. Because of this job, there is wastage of time and manpower. Company might have included this job in PMS because there was a motor failure in one of their other vessels. In such cases how can we convince the company to not to have this job in PMS. Also please send the Chief Engineer Handoff Audit Checklist.

  2. Thank you Daniel, would you be so kind to send me the ”Chief Engineer Handoff Audit Checklist”.

Please feel free to leave a reply!